Bluff Villas Maintenance

 

Bluff Villas

262 S. Sea Pines Dr.

Sea Pines Plantation, SC 29928

 

siteplan.jpg

 


For Information regarding particular building on the property please use links on the right side menu. For any questions or requests, Please use "Contact Us" link on the top Menu.

 


12/19/2011 Exterior Repair & Paint Project, Regime 56:

Scheduled start date for building 2 is December 20, 2011. Only stucco coating repairs and interior walkway paint work will take place before project shut-down for Holidays. Repair work will resume at Building 2 on January 3-rd, 2012. For more detailed information and project updates please use "Building 2" link on the right side menu of this page or use "Maintenance Calendar" link for project for schedule updates. 

 


11/01/2011 Exterior Repair & Paint Project, Regime 56:

     Scheduled start date for building #3 is November 3, 2011. For more detailed information and project updates please use "Building 3" link on the right side menu of this page or use "Maintenance Calendar" link for project for schedule updates.


09/28/2011 Exterior Repair & Paint Project, Regime 56:

     Scheduled start date on October 3, 2011. Repair work will star on building #5. For more detailed information and project updates, please use "Building 5" link on the right side menu of this page.


 

11/15/2010 Handrail Replacement, Regime 55:

     Rear side balcony hanrail replacement on Building 8 (Regime 55) started on November 15, 2010. For project progress and information, please use link "Building 8" on the right side menu.

 


06/25/2010 Handrail Replacement, Regime 56:

     Balcony handrail replacement on building 5 was completed on 06/24/2010. Replacement work continues on building 2. For more information please use "Building 2" link on the right side menu, or go to the "Maintenance Calendar" page for work schedules.

06/18/2010 Handrail Replacement:

     Balcony handrail replacement on building 3 was complete on 06/18/2010. Replacement work continues on building 5.  For more information please use "Building 5" link on the rigt side menu, or go to the "Maintenance Calendar" page for work schedules.

06/11/2010 Handrail Replacement:

     Balcony railing replacement started on building #3. For more information, please use "Building 3" link on the right side menu.

 


 

 

10/28/2009 EURO Construction Inspection (pdf)

 

 

10/26/2009 Advance Roofing Inspection (pdf) 

  

11/23/2009 Flat roof inspection on buildings 2, 3 & 5 (pdf)