Building 5

 

Regime 56, Building 5

262 S. Sea Pines Dr.

Hilton Head Island, SC 29928

 

Bld5Sign.jpg

Bld5Elevation.jpg

 

 

 

 

   

 

 

 

 

 

 

 


         2011 Exterior Repair And Paint Project:

 

Questions? Suggestions? Please use "Contact Us" link on the top menu of this page!!!

 

 


     11/22/2011 Project Update:

 

Exterior repair and paint work on Building #5 is almost complete. Stairway resurfacing shall start shortly after Owner's decission regarding finish coating. Floor tile repair on the left side entryway shall be performed last.

 

20111110011.jpg

 

 


 

20111110010.jpg

Repair project work complete on both ends of Building #5.

 


20111110009.jpg

Exterior repair and paint application on the rear side of Building #5 finished. All balcony handrails and aluminum fascia installed. All balconies are safe to use again.

 

 


20111110008.jpg 

New, factory primed Hardi® Trim fascia and Hardi® Vent soffit installed after roof overhang repair.

 


 20111110007.jpg

All damaged wood removed from roof overhang structure. New, pressure treated wood subfascia and 2x4 soffit framing installed in accordance to project Engineer's recommendations. 


20111110006.jpg

 Many damaged subfascia boards and soffit framing discovered in the process of the repair work.

 


20111110005.jpg 

As per design Professional's instructions, handrail fascia was removed from all balconies, to provide paint coating on the edge of balcony slab and seal behind handrail bracket.

 


20111110004.jpg

Stucco coating repairs performed on several areas around building #5 in accordance to instructions and specifications provided by design professional.


20111110003.jpg

 Scaffolding and power equipment being used at this repair project. We do ask all residents and guests to use extreme caution when entering/exiting building. Please limit all activities around construction area.

 


20111110002.jpg

 For Villa residents: Please, do not use sliding patio doors if you see this safety barrier with printed sign outside. It means, at least one rail was removed from the balcony and it is not safe to be on the balcony.

 


20111110001.jpg 

Repair project in progress. Scaffolding erected along the rear side of the building.

- - - - - - - - - - - - - - - - - - - - - - - - -  

      10/05/2011 - Update:

Exterior surface wash is scheduled for Friday, October 07, 2011, Monday, October 10, 2011 and Tuesday, October 11. For those Home Owners who have water and cleaner sensitive furniture and belongings in the  balconies or patios, we recommend to remove them for the dates indicated above. It is not necessary to remove your furniture for entire duration of the project, though EURO Construction will not be responsible for any belongings left in the balconies and/or patios.

- - - - - - - - - - - - - - - - - - - - - - - - -

     2011 Exterior Repair and Paint Project

 

scheduled to start on October 03/2011  

    


 06/25/2010 Update:

     Balcony handrail replacement on building 5 completed on 06/24/2010, Town inspection scheduled for Monday, June 28, 2010.

 


06/25/2010 Update:

     New balcony Handrails installed on units 1764 & 1756.

20100625bluff5bldunit1764.jpg 

     New balcony handrails installed on units 1765 & 1757.

20100625bluff5bldunit1765.jpg

     New balcony handrails installed on units 1763 & 1755.

20100625bluff5bldunit1763.jpg

     New balcony handrails installed on units 1766 & 1758.

20100625bluff5bldunit1766.jpg

06/22/2010 Update:

     New balcony handrails installed on units 1763 & 1755. Waiting on fascia delivery for unit 1755.

20100622bluff5bldunit1763.jpg 

 

     New balcony handrails installed on units 1762 & 1754. New braces instaled for fabric awning at unit 1762.

20100622bluff5bldunit1762.jpg 

 

     New balcony handrails installed on units  1766 & 1758. Waiting for fascia delivery.

20100622bluff5bldunit1766.jpg

 

06/21/2010 Update:

     New balcony handrails installed on units 1769 & 1761.

20100621bluff5bldunit1769.jpg 

     New balcony handrails installed on units 1767 & 1759. Handrail replacement in progress on units 1766 & 1758.

20100621bluff5bldunit1767.jpg 

 

06/18/2010 Update:

     Balcony handrail replacement started on Friday, June 18, 2010 on Building 5. New, aluminum, powder coated handrails installed on balconies of Units 1760 (second floor) and 1768 (thrid floor). Handrail replacement work will continue on Monday, June 21-st, 2010 on units 1761 and 1769.

20100619bluff5bldunit1768.jpg

 


06/07/2010 Handrail Replacement: New handrail installation on Building #5 should start on June 18-th., 2010 and complete on June 25, 2010. For updated project schedules please use a link on the right side menu to "Maintenance Calendar".

 


 

 

04/20/2010 Aluminum laders installation on the flat roof.

Left side heat pump deck:

20100420_blfvl5left2.jpg

Right side heat pump deck:

p4202479.jpg

 


12/20/2009 Final picture of the flat roof deck. Building #5

Final pictures of the flat roof deck on the left side of building #5

 20100112_building_5b.jpg

20100112_building_5b2.jpg

Final pictures of the flat roof deck on the right side of building #5

 20100112_building_5a.jpg

20100112_building_5a2.jpg

12/15/2009 Sagged roof repair over the left side entry of building 5.

Install fascia board and fascia trim. Install new select cypress 1x6 T&G ceiling boards. Re install rain gutter after paint work.

20091214_bluf5-2.jpg

20091214_bluf5-3.jpg

12/14/2009 Sagged roof repair over the left side entry of Building 5. 

 

Set up scaffolding. Secure top ends of the rafters using metal angles. Brace bottom part of the rafters. Remove rain gutter, remove fascia board. Jack up sagged part of the roof.

20091214_bluf5.jpg

20091214_bluf5-1.jpg 

12/01/2009 Sagged roof inspection over the left side entry to Building 5:

 

     Sagged roo over the left side entry of building 5 was inspected by EURO Construction, Inc. on December 1-st., 2009 by removing ceiling boards from lower section of entry roof. Only minor moisture damage to the fascia board was found during the inspection.

20091201bld5pic001.jpg 

      Main reason why roof sag took place, was determined to be poor quality original construction. There is a clear evidence of failed nailing attachement between 2x6 rafters and fascia boards on top and bottom part of the roof.

20091201bld5pic002.jpg

Large gaps exist between rafter ends and bottom fascia board. No anchoring devices, such as clips, metal angles, were installed at the time of original construction. Unrestricted condition of the main elements of the roof framing, caused movement of the framing parts and resulted in roof sag.

20091201bld5pic003.jpg

     Same condition exist at the top section of the subject roof. Rafters were installed using toe nailing connection to the top fascia board. Due to the dimensional changes in the wood properties over extended period of time, nailed connections have partially failed, resulting in unrestricted movement conditions in the lower roof section.

20091201bld5pic004.jpg

Existing condition of the roof framing may eventually lead to roof structure collapse from the live load on the roof surface.

20091201bld5pic005.jpg