                    2011 Exterior Repair And Paint Project:

 

 


12/22/2011 Project Update:

     All project work is almost finished on building #3. Fence and bench rebuild is in progress. Aluminum scaffolding shal remain erected untill January 3, 2012, when repair work will resume at Building #2.

    

      Soffit and fascia repair on the front-right side complete. Stucco repair and exterior paint work complete. New, wood handrail installed on the stairway. New, aluminum powdercoated handrails installed in inside landings.

eur_1650.jpg 

 

        Soffit and fascia repair at the front-left side complete, stucco repair and exterior paint work complete

eur_1652.jpg

 

Soffit and fascia repairs on the rear side comple. Stucco repair and exterior paint complete. All balcony handrails, previously removed for paint work have been reinstalled.

eur_1655.jpg

 


 

 20111110015.jpg

 Exterior wood repair and paint work in progress on the rear side of building #3. After November 28-th, 2011, we will start erectign scaffolds on the left-front side of the building.


 20111110013.jpg

 Part of rear side of building #3 was also finished before Thanksgiving.

 


 

20111110012.jpg

11/23/2011 Update:

Exterior repair and paintwork finished on the right side end of building #3 


 

   Exterior Repair and Paint work scheduled to begin at Building 3 on 11/03/2011.  For the first four or five working days, it will be mostly stucco coating repairs at exterior corners, setting up scaffolding, removing rear side privacy fencing.

     Exterior soft wash for Building #3 is scheduled for Tuesday, November 8-th, 2011 (subject to change).

  

 


 11/23/2010 Screen Enclosure:

     New, pwdercoated aluminum screen enclosure restored for unit 1741 at Building #3. Please refer to pictures below for exterior and interior look.

 

Exterior view:

20101124bluff56unit1741pic002.jpg

 

20101124bluff56unit1741pic001.jpg

Interior view:

 

20101124bluff56unit1741pic003.jpg


20101124bluff56unit1741pic004.jpg

06/18/2010 Update:

     Balcony handrail replacement on building #3 complete, two screened-in porches and one awning removed. Paint touch-up work in progress and should be finished by the end of business day on Friday, June 18-th, 2010

20200617bluff3bldunitfinish.jpg 

 20200617bluff3bldunitfinish2.jpg

 

06/15/2010 Update:

 

     Balcony Handrail replacement in progress at units 1730 & 1744. Fabric awning removed from balcony of unit 1744 per ASI request.

20100615bluff3bldunit1730.jpg 

 

     Balcony handrail replacement finished at units 1731 & 1745;

20100615bluff3bldunit1745.jpg 

 

     Balcony Handrail Replacement in progress at units 1733 & 1743;  Screen porch structure removed from balcony of unit 1743 per Regime 56 request. Screen porch structure removed from porch of unit 1725 per Regime request.

20100615bluff3bldunit1743.jpg

 

     Balcony handrail installation finished at units 1732 & 1742;

20100615bluff3bldunit1742.jpg 

 

 06/11/2010 Update:

     Balcony handrail replacement in progress on units 1732, 1742 & 1733;

 

20200611bluff3bldunit1742.jpg

      Existing Balcony handrails on unit 1732 and 1742:

20100610bluff3unit1732ex.jpg

 


06/10/2010 Handrail Replacement Update:  New Handrails for building #3 were delivered to Bluff Villas on Thursday, June 10/2010. All handrails inspected by Charlie Walczak and Valdas Stankevicius and aproved for installation. Handrail replacement work will start on Friday, June 11, 2010.


06/07/2020 Handrail Replacement: Due to some technical dificulties with fabrication of handrails, installation was delayed untill June 10, 2010. For updated project schedules please use a link on the right side menu to "Maintenance Calendar".


 

04/20/2010 Aluminum laders installation on the flat roof. Building #3

Left side heat pump deck:

20100420_blfvl3left1.jpg

 20100420_blfvl3left.jpg

Right side heat pump deck:

20100420_blfvl3right.jpg

20100420_blfvl3right1.jpg


12/20/2009 Final picture of the flat roof deck. Building #3 

Final pictures of the flat roof deck on the left side of building #3

 20100112_building_3b.jpg

20100112_building_3b2.jpg

Final pictures of the flat roof deck on the right side of building #3

 20100112_building_3a.jpg

20100112_building_3a2.jpg

12/10/2009 Moisture damage repair to the flat roof deck on the left side of building #3

Install new pressure treated rim board and 2x8 joists with HD galvanized joist hangers (in compliance with IBC2006 code). Apply pressure treated CDX roof plywood.  

20091211_bluf3-2.jpg 

Remove and dispose of roof membrane over the damaged flat roof deck area on the left side of building 3. Remove and dispose of plywood, joists and rim board.

20091211_bluf3.jpg

20091211_bluf3-1.jpg