Tanglewood Building 900
April 16 update:
Front side elevation view:
Siding and trims completely installed. Building Service yard fences, replacing front side stairs;
Left side elevation view:
Siding installation in progress;
Right side elevation view:
Right side of building 900 completely done
April 07 update:
Front Side elevation View:
Siding installation in progress.
Rear Side elevation View:
Balconies demolition and rot repairs complete. Siding and corners is completely installed. All windows and sliding doors replaced on the rear side.
Left Side elevation View:
Left side elevation view of Building 900. New windows installed. Siding and trim installation complete.
April 01 update:
Rear side elevation View:
Balconies demolition and rot repairs complete. Siding and corners is completely installed. All windows and sliding doors replaced on the rear side. New railing installation in progres.
Right side elevation view:
Siding installation in progress
Front side elevation view:
Repairing damaged framing, installing new plywood and Tyvek Home Wrap. New Windows and entry door is completely installed.
March 25 update:
Front side elevation view:
Old siding removing in progress.
Right side elevation view:
The old siding removed. Repairing damaged framing, installing new plywood and Tyvek Home Wrap. New Corners and Windows trim installed. Siding installation in progress.
Rear side elevation view:
All old siding has been removed.
Repairing damaged framing, installing new plywood and Tyvek Home Wrap. New corners and windows trims installed. Siding installation in progress.
March 18 update
Front side elevation view:
Rear side elevation view:
Sliding door replacement in progress.
Right side elevation view:
Old siding removed; damage reppair finished; new windows and louver vent installed; Ready for siding and trim installation.
March 10 update
Rear side of building 900
Right Side of building
Dear Villa Owners/Tenants,
Renovation work on building 900 is scheduled to start on 03/06/2008. Any villa Owners who have decided to have Light fixture installed in your balcony, please contact EURO Construction Office A.S.A.P.
All home owners and/or tenants shall use extra caution when entering and exiting building, also walking around stacked materials in parking lot. Please do not park your cars in front of building #900 left side wall during the work hours (7:00AM - 5:00PM).
Please remove furniture, plants and other belongings from your balconies and front entrance decks. We also recommend to remove any hanging objects from exterior walls (pictures, paintings, mirrors, etc.). Please Note, EURO Construction, Inc. will not assume responsibility for missing or misplaced belongings from your balcony or outside your front door.
Thank you for your cooperation !!!