Tanglewood Building 200

tgl200rearfinal.jpgBuilding #200 Final Pictures

 

tgl200frntfinal.jpg

P1010025.jpg

P1010026.jpg

 September 25, 2007 Construction Update

 

  • Siding replacement and wood rot repairs are finished on the rear side.
  • New windows and sliding patio doors installed for all 6 units in building 200.
  • All balconies rebuilt, Handrail installation at the final stages 

tgl200rearjpg.jpg 

tgl200side.jpg 

  •  Siding installation and wood rot repairs are finished on the front and right side of building 200.
  • Windows and new entry doors installed.
  • Interior trim installation in progress.
  • Entry stairs and bike storage fences finished
  • Acrylic caulk application in progress on the front elevation

tgl200frnt.jpg

 

 

September 07, 2007 Construction update

  • Building #200 rear side all old siding has been removed.
  • Building #200 rear side making wood rot inspection. Repairing damaged framing, installing new plywood and Tyvek Home Wrap.
  • Building #200 rear new siding on unit 201 installed. Moving further with new siding installation to units 203 & 204.
  • Building #200 all new corners and windows' trims installed on side wall.
  • Building #200 new siding installed on 3/4 of side wall.
  • A/C unit fence installed
  • Unit 201 bicycle storage fence finished
  • Unit 201 stair railings will be finished today 

 

P1010365.jpg

P1010367.jpg

P1010368.jpg

P1010370.jpg

August 30, 2007 Construction update

  • Left side wall all old siding removed.
  • New windows installed on left side wall
  • Front side siding will be finished today
  • Rear side #201 unit sliding door will be changed today
  • First and second floor new balconies framing constructed
  • Unit 202 front stairs railing completed

 

P1010352.jpg

P1010353.jpg

 

P1010355.jpg

P1010354.jpg

August 27, 2007 Construction update

  • Front side siding installation almost finished
  • Stairway railing trimmed
  • Unit 202 bike yard fence finished
  • Unit 202 railing installation in progress
  • Building #200 left side and rear side wall renovation started.
  • Removing old siding boards, inspecting plywood, construction framing for wood rot.
  • Fixing damaged framing, installing new plywood and covering with Tyvek Home Wrap.
  • Installing new windows and sliding doors on first floor.
  • Demolishing first floor balconies

 

P1010308.jpg

P1010309.jpg

P1010310.jpg

P1010311.jpg

P1010312.jpg

P1010313.jpg

P1010314.jpg

P1010316.jpg

P1010317.jpg

 

August 17, 2007 Construction update

 

  • Front side new siding installation started. Building's front right side and first floor siding installation completed.
  • Stairs to second floor reconstructed
  • Stair trimming and railing trimming in progress
  • New safet installation on first and second floor finished
  • Unit 201 and 202 entrance deck floor desks changed.
  • Windows and doors flashing and trimming finished

P1010269.jpg

 

P1010270.jpg

P1010271.jpg

P1010272.jpg

P1010278.jpg

 

August 08, 2007 Construction update

  • Building #200 front old siding removing in progress
  • Removing wall sheetrock covering
  • Making inspection for framing wood rot
  • Installing new plywood and Tyvek Home Wrap
  • Replacing front door and windows
  • Installing flashing around doors and windows
  • Old railigs removed from stairway
  • Ceiling safet removing
  • Next week will start unit 201 and 203 old siding removing and windows changing new railing installation

 

 

P1010228.jpg

P1010229.jpg

P1010230.jpg

P1010231.jpg

P1010232.jpg

P1010233.jpg