September 25, 2007 Construction Update
- Siding replacement and wood rot repairs are finished on the rear side.
- New windows and sliding patio doors installed for all 6 units in building 200.
- All balconies rebuilt, Handrail installation at the final stages
- Siding installation and wood rot repairs are finished on the front and right side of building 200.
- Windows and new entry doors installed.
- Interior trim installation in progress.
- Entry stairs and bike storage fences finished
- Acrylic caulk application in progress on the front elevation
September 07, 2007 Construction update
- Building #200 rear side all old siding has been removed.
- Building #200 rear side making wood rot inspection. Repairing damaged framing, installing new plywood and Tyvek Home Wrap.
- Building #200 rear new siding on unit 201 installed. Moving further with new siding installation to units 203 & 204.
- Building #200 all new corners and windows' trims installed on side wall.
- Building #200 new siding installed on 3/4 of side wall.
- A/C unit fence installed
- Unit 201 bicycle storage fence finished
- Unit 201 stair railings will be finished today
August 30, 2007 Construction update
- Left side wall all old siding removed.
- New windows installed on left side wall
- Front side siding will be finished today
- Rear side #201 unit sliding door will be changed today
- First and second floor new balconies framing constructed
- Unit 202 front stairs railing completed
August 27, 2007 Construction update
-
Front side siding installation almost finished
-
Stairway railing trimmed
-
Unit 202 bike yard fence finished
-
Unit 202 railing installation in progress
-
Building #200 left side and rear side wall renovation started.
-
Removing old siding boards, inspecting plywood, construction framing for wood rot.
-
Fixing damaged framing, installing new plywood and covering with Tyvek Home Wrap.
-
Installing new windows and sliding doors on first floor.
-
Demolishing first floor balconies
August 17, 2007 Construction update
- Front side new siding installation started. Building's front right side and first floor siding installation completed.
- Stairs to second floor reconstructed
- Stair trimming and railing trimming in progress
- New safet installation on first and second floor finished
- Unit 201 and 202 entrance deck floor desks changed.
- Windows and doors flashing and trimming finished
August 08, 2007 Construction update
- Building #200 front old siding removing in progress
- Removing wall sheetrock covering
- Making inspection for framing wood rot
- Installing new plywood and Tyvek Home Wrap
- Replacing front door and windows
- Installing flashing around doors and windows
- Old railigs removed from stairway
- Ceiling safet removing
- Next week will start unit 201 and 203 old siding removing and windows changing new railing installation