270 Stoney Creek
August 27, 2007 Construction Updates:
- Magazine table installed
- Kitchen appliances installed
- Tile between cabinets installed
- Carpet in first floor guest room, second floor guest room and master bedroom installed
- New faucets, toilets, sinks installed in bathrooms
Wood floor matching with wood samples
August 08, 2007 Construction update
- Cabinetry countertops installed
- Crown molding for kitchen cabinetry installed
- Hardwood floor installed
- All ceiling lightening installed
- Fans in living room and master bedroom installed
- Air conditioning working and control panels installed
- Ventilation hole grids installed
- Stairs to second floor installed
- Railing for stairs installed
- Magazine table installation in progress
- Master bathroom and second floor guest bathroom tile installation finished
- Smoke detectors installed
- All painting work finished
July 19, 2007 Construction update
- All walls and ceiling painted
- Kitchen cabinetry installed
- All power outlets and switches installed
- First floor guest bathroom and master bathroom tiles installation finished
- Second floor guest bathroom tile installation in progress
- All door adjustment in progress
- New ac ventilation pipes installed
- Electrical boxes for lights installed
- New panels installed in service room
- New plumbing pipes installed
June 22, 2007 Construction update
- Interior door installed
- Door triming finished
- Wall preparation for painting in progress
- Kitchen bar framing built
- Crown molding installation will be finished tomorow
- Windows installed 3" deeper
May 25, 2007 Construction update
- Interior door installation has started
May 10, 2007 Construction update
- Sheetrock installation finished at almost all rooms
April 26, 2007 Construction update
- Interior door ordered and delivery planed for 3rd of May
- Stairs to second floor framin finished
- Sheetrock installation work starts tomorow
February 16, 2007 Construction update
- Prepared tranch for plumbing lines replacement in kitchen
- Prepared opening in floor for beam support footing
- Prepared tranch for plumbing lines replacement in downstairs bathroom
- Framed new closet in downstairs bedroom
- Framing finished for owner's closet upstairs to allow for packet door
Renowation work has been resumed on Tuesday February 13th after asbestos abatement. Building permit was issued February 2, 2007.
Below are some progress pictures.