        May 28 update:

        Front side elevation view:

Painting in progress:

20080528_front.jpg

        Left side elevation view:

Painting in progress:

20080528_side.jpg

        Rear side elevation view:

Ready for painting:

20080528_rear.jpg   

        May 16 update:

        Front side elevation view:

Ready for painting:

20080516_front.jpg

        Left side elevation view:

Ready for painting;

20080516_left.jpg

        Rear side elevation view:

Deck floors & railings installation in progress. Siding installation in progress: 

20080516_rear.jpg

        May 09 update:

         Front side elevation view:

Siding installation and wood rot repairs are finished. Windows and new entry doors installed. Stairs replacement and service yard fences building in progress.

20080509_front.jpg

        Left Side elevation view:

Siding installation in progress:

20080509_side.jpg

        Rear Side view:

90% of old siding removed. Windows and sliding doors replacement in progress.

20080509_rear.jpg

        May 02 update:

        Front Side

 Siding Installation In Progress

20080502_front.jpg

        Rear Side Elevation View:

Old siding Removing in progress. All balconies destroyed. Windows and Sliding doors replacement in progress.

20080502_rear_side.jpg

       Left Side Elevation View:

Corner trim installation in progress

20080502_side.jpg

       April 28 update:

       Front Side Elevation View:

 Old siding removed. Wall inspected for wood rot. New plywood and Tyvek Home Wrap installed. Entry door and windows already installed. Trim and siding installation work in progress.

20080428_front.jpg

        Rear side elevation view:

Building a new balcony.

20080428_rear.jpg

       April 23 update:

       Front Side:

Old siding removing in progress. Windows and Front entry door installation in progress.

20080423_front.jpg

       Left side elevation view:

Old siding removed, damage reppair finished, new windows installed. Ready for siding and trim installation.

20080423_side.jpg

       Rear side elevation view:

20080423_rear.jpg

       April 16 update:

       Left side elevation view:

The old siding removed. Repairing damaged framing, installing new plywood and Tyvek Home Wrap.

20080416_left_side.jpg 

       Front side elevation view:

20080416_front_view.jpg

                              Dear Villa Owners/Tenants,

 

     Renovation work on building 1000 is scheduled to start on 04/10/08.   Any villa Owners who have decided to have Light fixture installed in your balcony, please`contact EURO Construction Office A.S.A.P.

    All home owners and/or tenants shall use extra caution when entering and exiting building, also walking around stacked materials in parking lot. Please do not park your cars in front of building #1000 left side wall  during the work hours (7:00AM - 5:00PM).

     Please remove furniture, plants and other belongings from your balconies and front entrance decks. We also recommend to remove any hanging objects from exterior walls (pictures, paintings, mirrors, etc.). Please Note, EURO Construction, Inc. will not assume responsibility for missing or misplaced belongings from your balcony or outside your front door.

     Thank you for your cooperation !!!

Building 1000: Front.

20080306_front_side.jpg

Left side of building 1000

20080306_left_side.jpg

Rear side