Fazio Villa # 19

 

  Preliminary Villa Piling Plan

 Actual Villa Piling Plan

 

Villa # 19 Piling Repair Progress Plan

Post#

Excavated for

Inspection

Post

Condition

Beam

Shored

Post 

Removed

Rebar

Installed

Concrete Mix

Poured

Shim

Installed

Post

Treatment

Soil

Back Filled

1 10/7/2019            10/9/2019  10/28/2019 
2 10/7/2019  WR  10/8/2019  10/8/2019  10/8/2019  10/11/2019  10/18/2019    10/28/2019 
3  10/7/2019 WR  10/8/2019  10/8/2019  10/8/2019  10/11/2019   10/18/2019   10/28/2019 
4 10/8/2019            10/15/2019  10/28/2019 
5 10/8/2019  WR  10/9/2019  10/9/2019  10/9/2019  10/11/2019  10/18/2019    10/28/2019 
6 10/8/2019            10/9/2019  10/28/2019 
7 10/8/2019            10/14/2019  10/30/2019 
8 10/8/2019            10/15/2019   10/30/2019
9 10/11/2019            10/15/2019   10/29/2019
10 10/11/2019            10/15/2019  10/28/2019 
11 10/8/2019  WR  10/9/2019  10/9/2019  10/9/2019   10/11/2019  10/18/2019   10/28/2019 
12 10/8/2019            10/15/2019  10/30/2019 
13 10/8/2019  WR  10/14/2019   10/14/2019 10/14/2019  10/15/2019  10/23/2019    10/30/2019 
14 10/8/2019             10/15/2019 10/30/2019 
15  10/9/2019 WR  10/9/2019  10/9/2019  10/10/2019  10/11/2019  10/18/2019    10/29/2019 
16 10/8/2019            10/14/2019  10/28/2019 
17 10/8/2019            10/15/2019  10/30/2019 
18 10/8/2019            10/15/2019  10/30/2019 
19 10/8/2019            10/15/2019  10/30/2019 
20 10/8/2019  WR   109/2019 10/9/2019  10/9/2019  10/11/2019   10/24/2019   10/30/2019 
21 10/8/2019  WR  10/9/2019  10/9/2019  10/9/2019  10/11/2019  10/18/2019     10/30/2019
22 10/8/2019            10/15/2019  10/29/2019 
23 10/8/2019            10/15/2019  10/29/2019 
24 10/7/2019            10/14/2019  10/29/2019 
25 10/8/2019             10/14/2019 10/28/2019 
26 NO POST                 
27 10/10/2019  WR  10/10/2019  10/10/2019  10/10/2019  10/11/2019  10/18/2019     10/28/2019