Fazio Villa # 17

 Preliminary Villa Piling Plan

 Actual Villa Piling Plan

 

Villa # 17 Piling Repair Progress Plan

Post#

Excavated for

Inspection

Post

Condition

Beam

Shored

Post 

Removed

Rebar

Installed

Concrete Mix

Poured

Shim

Installed

Post

Treatment

Soil

Back Filled

1 8/6/2019   WR  8/8/2019 8/9/2019  8/9/2019  8/13/2019   8/21/2019    9/19/2019
2  8/6/2019  G           8/16/2019  9/19/2019 
3 8/6/2019   G           8/16/2019  9/19/2019 
4  8/12/2019           8/19/2019  9/19/2019 
5 8/12/2019            8/19/2019   9/19/2019
6  8/12/2019 WR   8/13/2019 8/13/2019  8/13/2019  8/15/2019  8/23/2019     9/19/2019
7 8/6/2019   G           8/19/2019   9/19/2019
8 8/12/2019   WR 8/15/2019  8/16/2019  8/16/2016  8/20/2019   8/27/2019   9/19/2019 
9 8/15/2019  WR   8/27/2019  8/27/2019 8/27/2019   9/10/2019 9/17/2019    9/19/2019 
10  8/12/2019           8/16/2019   9/19/2019
11 8/6/2019            8/16/2019   9/19/2019
12 8/14/2019            8/19/2019  9/19/2019 
13  8/14/2019           8/19/2019  9/19/2019 
14  8/15/2019  G           8/19/2019  9/19/2019 
15  8/6/2019  WR 8/12/2019  8/12/2019  8/13/2019  8/15/2019   8/21/2019   9/19/2019 
16  8/6/2019 WR   8/8/2019 8/9/2019   8/9/2019 8/13/2019   8/21/2019   9/19/2019 
17  8/8/2019 WR   8/8/2019 8/8/2019  8/9/2019  8/13/2019   8/21/2019   9/18/2019 
18  8/13/2019 WR   8/27/2019  8/27/2019 8/27/2019  9/10/2019  9/17/2019    9/19/2019 
19 8/16/2019            8/19/2019  9/19/2019 
20 8/7/2019  WR  8/9/2019  8/9/2019  8/9/2019  8/13/2019   8/22/2019   9/19/2019 
21  8/7/2019 WR   8/14/2019  8/14/2019 8/14/2019   8/20/2019  8/27/2019   9/18/2019 
22  8/7/2019           8/16/2019  9/18/2019 
23  8/7/2019           8/16/2019  9/18/2019 
24  8/7/2019           8/16/2019  9/19/2019 
25  8/7/2019  WR 8/8/2019 8/8/2019 8/9/2019 8/13/2019  8/23/2019    9/19/2019 
26                  
27