Lighthouse Villas Regime I

  

LIGHTHOUSE VILLAS RENOVATION PROJECT

 

 


  • 12/03/2008 - Sea Pines Plantation Building permit issued.   (Click Here)

 

  • 11/25/2008 - Town of Hilton Head Island Building Permits Issued.
    • Permit 1   (Click Here), Updated on 01/14/2009 
    • Permit 2    (Click Here), Updated on 01/14/2009

 


  • 10/29/2009 Final Inspection Passed; Congradulations to all Homeowners!!! Renovation project is ower. Please enjoy your new home!!!

 

  • 10/13/2009 Project Update:

 Unit #4 Service yard  gate installed

20091013lv2pic101.jpg 

Unit #5 Service yard gate installed

20091013lv2pic100.jpg

 Unit #4 Front.20091013lv2pic99.jpg

 Unit #5 Front

20091013lv2pic98.jpg 

  • 10/05/2009 Project Update:

Unit #5. Front

20091005lv2pic92.jpg

Unit #4. Front

20091005lv2pic93.jpg 

Left side of Building #2 (Unit #4)

20091005lv2pic94.jpg

20091005lv2pic95.jpg

Unit #4. Rear side

20091005lv2pic96.jpg 

Unit #5. Rear side

20091005lv2pic97.jpg 

  • 09/28/2009 Project Update:

 

Unit #4,5 Stucco siding installation

 20090928lv2pic82.jpg

20090928lv2pic83.jpg

 20090928lv2pic84.jpg

20090928lv2pic85.jpg

20090928lv2pic86.jpg

20090928lv2pic87.jpg

20090928lv2pic88.jpg

20090928lv2pic89.jpg

20090928lv2pic90.jpg

20090928lv2pic91.jpg 

  • 09/15/2009 Project Update:

 Unit #5 Front. Service yard fences builded. Ready for stucco siding 

20090915lv2pic80.jpg

 Unit #4 Front. Service yard fences builded. Ready for stucco siding

20090915lv2pic81.jpg 

  • 09/04/2009 Project Update:

 Hardiplank siding completely installed on left side of unit #4.

20090904lv2pic82.jpg

Unit #4. Hardiplank siding completely installed.

20090904lv2pic81.jpg

Unit #5. Hardiplank siding completely installed. 

20090904lv2pic80.jpg

  • 08/17/2009 Project Update:

 Unit #4,5 Front. New soffit framing.

20090817lv2pic69.jpg

20090817lv2pic70.jpg 

Unit #5 Front. New service yard storage.

20090817lv2pic71.jpg

 Unit #7.9 Front. Service yard fences ready for stucco siding installation.

20090817lv2pic72.jpg

20090817lv2pic73.jpg

 Unit #8.9 Front.20090817lv2pic74.jpg

Unit #8. Service yard gate.

20090817lv2pic75.jpg

 Unit #9. Service yard gate.

20090817lv2pic76.jpg 

Unit #9 Servise Yard

20090817lv2pic77.jpg

Left side of Unit #4: Building soffit.

20090817lv2pic78.jpg

20090817lv2pic79.jpg

  • 07/31/2009 Project Update:

     End wall of unit # 9. Hardiplank and siding application finished, Soffit panels and fascia trim installation finished, exterior application finished.

20090731LV2Pic64.JPG

     Rear side of unit #9 . Stucco and siding finished.

20090731LV2Pic65.jpg

     Rear side of units #6 & #7. Siding and trim installation on sunroom walls finished. Roof replacement in progress.

20090731LV2Pic66.jpg

     End wall of Unit #4. Siding removal in progress.

20090731LV2Pic68.jpg

     Front side of Unit #5. Outside shed and service yard fence demolished.

20090731LV2Pic69.jpg     Front side of Unit #6. Siding and trim installation finished. Service yard fence built, ready for electrical rough-in. Shingle roof replacement in progress.

20090731LV2Pic70.jpg 

     Front side of unit #7. Siding and trim installation finished. Service yard fence built, ready for electrical trim-out. Shingle roof replacement in progress.

20090731LV2Pic71.jpg

     Front side of units #8 & #9. Siding and trim installation finished. Stucco applied on lower level and service yard fences.

20090731LV2Pic72.jpg

     Building #1. Sealoflex flooring complete on entry patio of units # 1, 2 & 3.

20090731LV2Pic73.jpg

 

  • 07/17/2009 Project Update:

 Rear side of Unit #6,7. Siding Installation in progress:

20090717lv2pic68.jpg

20090717lv2pic67.jpg 

Rear side of unit #9

20090717lv2pic66.jpg 

Stucco siding finish coat installed on right side of building #2 (unit #9)

20090717lv2pic65.jpg 

  • 07/09/2009 Project Update: 

Unit: #7: New outside storage framing in proggres

20090709lv2pic61.jpg 

Unit #6: New outside storage framing in proggres

20090709lv2pic62.jpg 

Apply hard coat cement stucco on designated areas of building 2

20090709lv2pic63.jpg

20090709lv2pic64.jpg

  • 06/30/2009 Project Update:

Unit #7. Front door inallation

20090630lv2pic55.jpg 

Unit #6. Rear side:

20090630lv2pic54.jpg 

Unit#7. Rear side:

20090630lv2pic53.jpg 

  • 06/25/2009 Project Update:

Unit#8. New Sunroom (from Inside)

20090625lv2pic52.jpg 

Unit#7. New Sunroom (from inside)

20090625lv2pic51.jpg

Rear side of unit #6.

20090625lv2pic50.jpg

Rear side of Unit #7.

20090625lv2pic49.jpg

  • 06/15/2009 Project Update

 Unit # 7,8. Sunroom framing in progress.

20090615lv2pic45.jpg

 Unit #9. Interior Casement Instaled. Ready for painting

20090615lv2pic46.jpg

 Building #1.  Front Patio

20090615lv2pic48.jpg

Unit #8,9. Roof shingless replacement

20090615lv2pic47.jpg 

  • 06/10/2009 Project Update:

Building #1.  Front Patio

20090610lv2pic44.jpg

Unit #8. Ready for shingles replacement

20090610lv2pic43.jpg 

Unit # 7. Sunroom framing in progress.

20090610lv2pic42.jpg 

Unit # 6. Sunroom demolition in progress.

20090610lv2pic41.jpg

Unit#9. Service yard fences ready for stucco.

20090610lv2pic40.jpg 

Unit#8. Service yard fences ready for stucco.

20090610lv2pic39.jpg

  • 06/04/2009 Project Update:

Unit # 7.  Sunroom demolition in progress.

20090604lv2pic37.jpg

20090604lv2pic38.jpg

New service yard fences built for Unit # 920090604lv2pic36.jpg

Unit #8, 9 Front. Siding and trim installed and painted

20090604lv2pic34.jpg

20090604lv2pic35.jpg

  • 06/01/2009 Project Update:

 Unit #8,9 Front. Siding and trim installation in progress

20090601lv2pic33.jpg 

Unit # 9 End wall. Siding and trim installed.

20090601lv2pic32.jpg 

Rear side of units #8,9. Siding, corners, and trim  completely installed on the sunroom walls

20090601lv2pic31.jpg

  • 05/26/2009 Project Update:

Building#1, villas number sign installed.

0090526lv1pic75.jpg

0090526lv1pic74.jpg 

Unit #9. Rear side. Siding and trim installed

20090512lv2pic32.jpg

Right side of building #2: Hardisoffit installation:

20090512lv2pic31.jpg 

Unit #8,9. Hardi soffit and fashia bord installation:

20090512lv2pic30.jpg

  • 05/14/2009 Project Update:

 Exterior light installed on building #1

20090514lv1pic75.jpg

New, Kolbe French style patio door installed in sunroom of unit #9

20090514lv2pic30.jpg

  • 05/11/2009 Project Update:

 Sun rooms of units #8,9 from outside. Windows installed, tyvek and flashing applied.

20090512lv2pic26.jpg

20090512lv2pic27.jpg 

Insulation R-13 installation in unit #9 

20090512lv2pic28.jpg

New front entry doors with impact resistant glass installed on unit #9

20090512lv2pic29.jpg 

  • 05/04/2009 Project Update: 

Unit #9.  New, Insulated glass panels ordered from "Labbë Glass". Sun room framing in progress.

20090504lv2pic24.jpg

Demolition of rear side screen porch (Unit #8) finished. Slab prepared for new sun room framing.

20090504lv2pic25.jpg 

 

  • 04/28/2009 Project Update: 

      Unit #9, Sunroom demolition finished. Wood rot repair in progress under living room windows.

20090428LV2Pic17.jpg

      Unit #8. Sun room demolition in progress.

20090428LV2Pic18.jpg

  • 04/23/2009 Project Update:

  

 Demolition of rear side screen porch (Unit #9).

20090423LV2Pic16.JPG

 Right side gable wall framing fixed, sheathing applied. Ready for siding and hardisoffit

20090423LV2Pic15.JPG

  Unit #8. New soffit framing:

20090423LV2Pic14.JPG

 Unit # 8,9.  Roof structure above front entrance.  New soffit framing.

20090423LV2Pic13.JPG

20090423LV2Pic12.JPG

 

 

  • 04/10/2009 Project Update: 

      End wall of Unit #1. Stucco finish coat applied.

20090410LV1Pic67.jpg

      Unit #1. Rear bedroom wall. Stucco finish coat applied.

20090410LV1Pic68.jpg

     Unit #2. Living room wall. Stucco finish coat applied.

20090410LV1Pic69.jpg 

      Unit #2. Rear Bedroom wall.

20090410LV1Pic70.jpg

      Unit #3. Rear side wall. Stucco finish coat applied.

20090410LV1Pic71.jpg

     End wall of Unit #3. Stucco finish coat applied.

20090410LV1Pic72.jpg 

     Front side of Unit #3.

20090410LV1Pic73.jpg

     Front side of Unit #2. New service yard gate with hardware. Gate is made of 100% pure PVC materials, PVC cement adhesive and stainless steel screws. It Should realy last !!!

20090410LV1Pic74.jpg

          BUILDING 2:

     End wall of Unit #9. New, Pressure treated wood framing for second floor siding installation.

20090410LV2Pic09.jpg

     New soffit structure framed, ready for inspection.

20090410LV2Pic10.jpg

     Rear side of Unit #9.

20090410LV2Pic11.jpg

 

  • 04/08/2009 Project Update: 

      New PVC louver in service yard fence for proper air flow to heat pump in service yard.

20090408LV1Pic66.jpg

 

  • 04/06/2009 Project Update: 

      Final stucco coat applied on entire front side.

20090406LV1Pic62.jpg 

      Stucco texture is not very visible in the picture, though it looks realy good.

20090406LV1Pic63.jpg

      Service yard louver and gate installation should start this week.

20090406LV1Pic64.jpg

 

 20090406LV1Pic65.jpg

      Building 2:

     Siding and trim removed from front side wall of Units #8 & #9.

20090406LV2Pic05.jpg

    Wood rot repairs in progress on the front side.

20090406LV2Pic06.jpg

     Siding removal in progress on the side wall of unit #9.

20090406LV2Pic08.jpg

 

  •  04/03/2009 Project Update: 

      Brown coat stucco applied on most areas of exterior walls.

20090403LV1Pic52.JPG 

     Unit #1 with finish coat on the front walls.

20090403LV1Pic53.JPG

     Unit #2. Final coat applied on part of front wall.

20090403LV1Pic54.JPG 

      Unit # 3 Front side with brown coat applied.

20090403LV1Pic55.JPG

      Unit # 3 End wall. Siding and trim installed, brown coat stucco applied.

20090403LV1Pic56.JPG

     Unit # 3 rear side. Siding and trim installed, brown coat stucco applied.

20090403LV1Pic57.JPG

     Unit # 2 Rear side. Siding and trim installed, brown coat stucco applied.

20090403LV1Pic59.JPG

     Unit # 1 Rear side. Siding and trim installation finished. Brown coat stucco applied.

20090403LV1Pic60.JPG

     Unit # 1 Side wall. Siding and trim installation finished. Brown coat stucco applied.

20090403LV1Pic61.JPG

     Building 2:

           Demolition work started on Units # 8 & # 9

20090403LV2Pic02.JPG

     Service yard fences and outside storages taken demolished and disposed.

20090403LV2Pic03.JPG

     Unit #9

20090403LV2Pic04.JPG

 

  • 03/19/2009 Project Update: 

      Side wall of building 1 (Unit #1) prepared for stucco mesh and flashing inspection.

20090319LV1Pic44.jpg

      Hardiplank siding installation in progress on new sun room of Unit #1.

20090319LV1Pic45.jpg

      Stucco mesh and flashing application in progress around building 1. Painters are working on interior parts of windows for Unit #1.

20090319LV1Pic46.jpg

     Living room wall of Unit #2 prepared for inspection and stucco application.

20090319LV1Pic47.jpg 

      Finished sunroom of Unit #2.

20090319LV1Pic48.jpg 

       New Siding around French door.20090319LV1Pic49.jpg

     Stucco mesh and flashing almost ready for inspection on the front side of Unit #3.

20090319LV1Pic50.jpg

     New phone lines for Units 1-3 pulled outside and placed into conduit. Hargray is working on terminal box replacement and new lines termination. Units 1-3 may not have phone working properly at all the times during the work hours on 03/19/2009 and 03/20/2009.

20090319LV1Pic51.jpg

 

  • 03/18/2009 Project Update: 

      New front entry doors with impact resistant glass and new hardware installed on building 1.  Stained fiberglass has nice, naturall wood look.

20090313LV1Pic37.jpg

     Sun room of unit #3. Window and French door trim applied, Ready for siding application.

20090313LV1Pic38.jpg 

      Sun room of Unit #5. New drywall applied on walls and ceiling. Sanding and preparation for interior trim and paint in progress.

20090313LV1Pic39.jpg

      Sun room of Unit #5 from outside. Windows installed, Tyvek and flashing applied.  New soffit panels, fascia trim and roofing applied.

20090313LV1Pic40.jpg

    New service yard fences built for Units # 1-3. 4'x4' openings made for vertical louver to be installed after stucco application.

20090313LV1Pic41.jpg 

      Bottom part  of all exterior walls was waterproofed with Sealoflex. This will prevent water intrusion behind stucco and siding. 

20090313LV1Pic42.jpg 

      New Kolbe picture window installed in livingroom wall of Unit #1. New sheetrock applied under window and prepared for casing and interior paint.

20090313LV1Pic43.jpg

  

  • 03/03/2009 Project Update: 

     New Kolbe windows installed in sunroom of Unit #1. Soffit and fascia trim installation finished on sunroom roof structure.

20090303LV1Pic31.jpg

     New, Kolbe French style patio door installed in sunroom of unit #1, new windows installed in front and rear side bedrooms, new window in living room (facing Lighthouse road).

20090303LV1Pic32.jpg 

     New Kolbe windows and French style patio door installed in sunroom of Unit #3. New windows also installed in front and rea side bedrooms, living room. Soffit panel and fascia trim installation complete. Ready for roof installation over sunroom.

20090303LV1Pic33.jpg

     New window in front side bedroom of Unit #3.

20090303LV1Pic34.jpg 

     Wood rot repairs in the roof deck of Building #1 performed on February 25, 2009. New asphalt roof shingles applied with aluminum step flashings and dripedge. New boot pipes installed and rolled ridge vent applied over Units #1, 2 and 3. New roof application for outside storages and sunrooms scheduled for March 4, 2009.

20090303LV1Pic35.jpg

     Installation of new Front entry doors, Kitchen doors and storage doors in progress on Units # 1, 2 and 3.

20090303LV1Pic36.jpg 

 

  • 02/18/2009 Project Update: 

     New sun room construction finished for units #4 & #5. Exterior sheathing applied on the walls and roof deck. Electrical rough-in and window installation are next on the work schedule. (window installation may be delayd, due to necessary work for Building 1 to prepare for roof replacement and sheetrock installation.

20090218LV1Pic29.jpg 

      Sun room construction finished for Unit #3. Electrical rough-in finished. Building inspection passed on 02/18/2009 for all rough-in inspection items on entire building 1. For details on inspection items, please check "Work Shcedule" on the right side menu of this page.

20090218LV1Pic30.jpg 

Next step is to apply exterior sheathing and weather barier, Install windows and doors, finish fascia trim installation on the rear side to prepare for roof replacement.

 

  • 02/11/2009 Project Update: 

      Demolition of existing sun room in unit #3 finished. Wall framing in progress for new living room window.

20090211LV1Pic28.jpg

     New Kolbe window installed in the rear bedroom of Unit #3.

20090211LV1Pic27.jpg 

      Wood rot replacement in progress under living room windows of Unit #5.  New, Insulated glass panels ordered from "Island Glass". Sun room framing in progress.

20090211LV1Pic26.jpg

 

  • 02/05/2009 Construction Update:

     New sun room structure built for unit #4. Anchoring and hurricane strapping installation in progress.

20090205LV1Pic24.jpg 

 Existing sunroom demolished at unit #5. Severe wood rot found under living room windows.

20090205LV1Pic25.jpg 

 Wood ort on the left side of middle window.

20090205LV1Pic26.jpg 

 Wood rot under middle and right side windows.

20090205LV1Pic27.jpg 

 Wood rot under rigt side window by the fire wall. Repair work will require to remove glass from both windows.

20090205LV1Pic28.jpg

  •    
  • 01/23/2009 Construction Update:

     Sun-room framing finished for unit #2.  Window/door openings built, exterior sheathing applied, Necessary anchoring installed. Roof construction finished on 01/22/2009. Hurricane ties installation in progress.

20090121_lv1pic22.jpg

     Sunroom framing finished for unit #1. Roof assembly in progress.

20090121lv1pic23.jpg 

 

  • 01/16/2009 Construction Update:

     Both building permits were replaced/updated on January 16/2009 to add plumbing and air conditioning services. All exterior water spigots will be removed and lines capped before new exterior sheathing application. New exterior grade spigots with "Back-flow Preventer" will be installed after final stucco coat application. Plumber will also fix existing water heater drain and pressure release lines. Air conditioning services added to both building permits, in case building #2 needs re-locations or other type of service associated with building code requirements.

      Exterior storage framing finished on Unit # 3. Roof covered with Ice & Water shield, new electrical lines installed. Heat pump in service yard has been relocated to comply with building code. New coolant lines have been rerouted through storage.

20090116 LV1Pic17.jpg

 

     Exterior storage framing finished on Unit # 2. Roof covered with Ice & Water shield, new electrical lines installed. Heat pump in service yard has been relocated to comply with building code. New coolant lines have been rerouted through storage.

20090116 LV1PIC18.jpg 

 

     Exterior storage framing finished on Unit # 1. Roof covered with Ice & Water shield, new electrical lines installed. Heat pump in service yard has been relocated to comply with building code. New coolant lines have been rerouted through storage. 

 20090116 LV1Pic19.jpg

     Main structure of the new sun-room is framed for Unit #2. New anchor bolts and tie-downs installed. Ceiling assembly in progress. New window openings framed in bedroom and living room. Hurricane ties installed on all rafter tails. New anchor bolts installed in the main building code according to IBC-2006.

20090116 LV1Pic21.jpg 

      Old sun-room structure demolished and disposed at Unit #1. New sun-room framing in progress. New window openings framed in bedroom and living room. New hurricane ties installed on all rafters and new anchor bolts added to the main walls as per code requirements.

20090116 LV1Pic20.jpg

  • 01/07/2009 Construction Update:

     New exterior storage walls framed with openings for new double doors.

20090107 LV1Pic11.jpg

 

     Right side gable wall framing fixed and sheathing applied. Ready for siding installation. Soffit panels and fascia trim boards installed on the left side.

20090107 LV1Pic12.jpg

     Soffit panels and fascia trim boards removed and disposed on the rear side of building 1. 

20090107 LV1Pic13.jpg

 

 

  • Demolition of rear side screen porch (Unit #2) finished. Slab prepared for new sun room framing.

20090107 LV1Pic14.jpg 

      Existing sun room of Unit #1 is next to be removed.

20090107 LV1Pic15.jpg

     Left side gable wall framing fixed, sheathing applied. Ready for siding application upon installation of gable vent.

20090107 LV1Pic16.jpg

 

  • 12/18/2008 Construction Update:

     All siding and trim boards removed on the front side of building 1. Exterior storage structures demolished. Wood rot repairs and framing work in progress.

20081218 LV1Pic7.jpg

     Sliding patio doors removed from front side bedrooms of Units #1 and #2. Openings framed for new windows.

20081218 LV1Pic8.jpg

  • 12/12/2008 Construction Update:

     Renovation Project started today, on building 1 (Villas 1-3). Unit # 1 in the picture below. Front side wall. Service yard fence removed, Exterior storage structure demolished and disposed. Exterior fascia trim, soffit panels, siding and trim removed and disposed.

20081212 LV1Pic1.jpg

     Unit # 1, Roof structure above front entrance. No hurricane clips were installed at the time of original construction. Roof trusses were just toe-nailed to wall plate.

20081212 LV1Pic2.jpg 

     Unit # 1. Front side bedroom wall on the right side of entrance. No anchor bolts to tie down wall framing to concrete slab.

20081212 LV1Pic3.jpg 

     Unit #1, Exterior wall on the left side of the front entrance. Wood rot in the sill plate.

20081212 LV1Pic4.jpg

     Unit #1. Wood rot in the sill plate, on the left side of the service door.

20081212 LV1Pic5.jpg

     Unit # 1. A/C coolant lines and control wiring need to be moved underground and placed in PVC conduit. We also suggest moving compressor unit to the front side of the service yard, so compressor could be placed directly in front of luvered vent.

20081212 LV1Pic6.jpg 

 

02/14/2007

 

     Project site consists of two buildings:

  • Building one - single story building with three residential units #1, 2 & 3

   lths_villas_frnt_071018.jpg

  • Building two - two story building with six residential units  # 4, 5, 6, 7,`8 & 9

lths_villas_frnt_071018-2.jpg

 

Recommendations:

       At the time of exterior renovation it is most practical and cost efficient to replace, upgrade and repair as many exterior/interior building elements as possible. We recommend all Villa Owners to carefully inspect Villa interior/exterior before deciding on the work scope for renovation project.  If your A/C compressor looks like the one in the picture, its time to replace it.

 p1012924.jpg

Chech your A/C handler too or have your HVAC company to inspect it. there are at least two A/C systems on the property that need attention.

Check around your windows and service doors (in service yard). We have noticed moisture damages in some of the service doors. It is always a good idea to open your door and inspect door jambs and trim at the bottom.

p1012920.jpg

Take a pocket knife or small screw driver and see if wood is soft at the bottom of the door. Check drywall inside, around windows and doors for brown stains to determine if door/window has been leaking.

On the windows, you can inspect aluminum frame joints at the corners to see if any joint separation is vissible. Also check rubber seal between glass and frame, to see if it has been dryed and cracked.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

      For the service yards gates, we would recommend to install light weight aluminum square tube gates. It would be long lasting and low maintenance solution. The cost for one 36" x 60" metal gate installed is $ 650.00 - $ 1,500.00 depending on the design. next option wood be pressure treated frame gate with composit siding boards such as KLEER wood grain boards with exterior grade, galvanized hinges and latch. Construction and installation of this type gate is around $ 250.00 - $ 350.00 depending on design. 

 p1010805.jpg

     Existing sunrooms on the rear side of building display signs of localized wood rot and elevated moisture in trim boards and structural lumber due to long-term exposure to weather and improper flashing installation and/or flashing absence.

p1010810.jpg

     Previous attempts to fix this problem are clearly visible on some Sunrooms exterior. This should not be considered as proper way to address wood rot in load bearing structure and it may not pass final inspection after project is finished.

 

     There are numerous phone and TV cable lines attached to exterior siding and trim boards.  In the picture below, there is phone junction box,

p1012839.jpg

that is missing cover. All wires and junctions are exposed to the weather. All wires are running up to the attic level and penetrating wood siding.

In many places, penetrations made by TV and Phone company were performed without any consideration about aesthetical appearance nor attempt to seal penetration hole to prevent water intrusion inside wall structure.

p1012844.jpg

Exposed electrical wires in service yards and outside some carolina rooms don't comply with current codes. All exterior electrical wires shouls be installed in the conduit.  Exposed bulb light fixture in the outside storages is against the current Fire Code.

     There is good example of Code violation in the service yard of Unit # 9. Large A/C compressor is installed directly in front of electrical metter and blocking access to the meter. By the code, there should be minimum of 36" clearance in front of any electrical meter.

p1012851.jpg

A/C system disconnects should also be placed on the surface of new service yard wall. Some of them are in such condition, that replacement should be considered. Disconnects located like the one in picture below, will not pass any inspection and they are useless.

p1012912.jpg

 A/C handlers shall be easy accessible for service and repair. Should Villa Owners decide to replace all outside storage doors with new double door, we would recommend to install double door such way, that one half of the door would be located directly in front of A/C handler.